4-26.
What field riveting symbol shows
that the rivet should be
countersunk on both sides?
4-27.
The shop riveting symbol
shows
that the rivet should be installed
in what way?
1.
Countersunk and chipped on the
near side
2.
Countersunk and chipped on both
sides
3.
Countersunk and chipped on the
far side
4.
Riveted with two full heads
4-28.
What shop riveting symbol shows
that the rivet should be
countersunk and not over 1/8 inch
high on the far side?
IN ANSWERING QUESTIONS 4-29 THROUGH 4-33,
SELECT FROM THE FOLLOWING LIST THE TYPE OF
DRAWING DESCRIBED IN THE QUESTION.
A.
Layout
B.
General
C.
Fabrication
D.
Erection
E.
Falsework
4-29.
These drawings show where temporary
supports will be used in the
erection of difficult structures.
1. B
2. C
3. D
4. E
4-30.
The number of these drawings needed
depends on the size and nature of
the structure and the complexity of
the operation.
1. A
2. B
3. C
4. D
4-31.
These drawings provide information
on the location, alignment, and
elevation of the structure and
principle parts in relation to the
ground at the site.
1. A
2. B
3. C
4. D
4-32.
These drawings contain necessary
information on the size, shape,
material,
and provisions for
connections and attachments for
each member.
1. B
2. C
3. D
4. E
4-33.
These drawings show the location of
the various members in the finished
structure.
4-34
4-35
1. B
2. C
3. D
4. E
Contours, boundaries, roads,
utilities, trees, structures, and
other physical features of a site
are shown in what type of
construction plan?
1.
Framing
2.
Floor
3.
Plot
4.
Site
What type of construction drawing
shows plans and elevations on a
small scale?
1.
Plot
2.
General
3.
Detail
4.
Site
IN ANSWERING QUESTIONS 4-36
AND 4-37,
REFER TO THE FOUNDATION PLAN
IN FIGURE 7-9 IN THE TEXTBOOK.
4-36.
The main foundation consists of
what material(s)?
1.
An 8-inch block wall on a
10-inch footing
2.
An 8-inch block wall on a
12-inch footing
3.
A 10-inch block wall on an
18-inch footing
4.
A 10-inch block wall on an
18-inch footing
24